Rapid Turn-Around-Time on Results


The old adage "time is money" also applies to the environmental testing business. That is why our standard turnaround time is five working days. Most environmental labs are not designed for rapid TAT - we are. Same day, next day, two day and three day results are our routine. If fast results are important then Teklab is the laboratory for you. We have designed our lab to operate for the rapid TAT clients. Whether you have a large lengthy project or a small one time project, Teklab is designed to deliver next day, two day and three day results as a normal course of business. 


Here is a look at a history of our turn-around-times.

2018 Performance   2017 Performance
Month # of Work Orders      # of Tests       Average Days   
to Complete  
  
            Month   # of Work Orders     # of Tests     Average Days   
to Complete
 
January 1718
18164 3.39   January             1642
19867
3.76
February  1711
22990
3.69
  February 1694
24969 4.39
March 1859
22953
3.42
  March  1934
21755 3.55
April


  April  1635 25711
3.78
May


  May 1809 23560
3.49
June


  June  2038 24484
3.67
July


  July  1784 20849 3.66
August


  August  1981 22200 3.38
September    


  September  1805 19937 3.42
October


  October  1822 25813 3.59
November


  November  1782 24415 3.79
December        

  December 1670 20290 4.06


   

 
 2016 Performance    2015 Performance
 Month  # of Work Orders    # of Tests     Average Days
to Complete    

   Month  # of Work Orders   # of Tests  Average Days
to Complete 
 January  1636  15274
 3.14
   January 1420 16721 3.14
 February  1629  15076  3.27
   February 1372 17742  3.15 
 March  1934  22827  3.47
   March 1650 20278  3.09 
 April  1852  22853
 3.39     April 1702 25408  3.45 
 May  1866
 22149
 3.71    May 1658 22842  3.53 
 June  1919  24187
 3.76
   June 1860 21866  3.22 
 July  1822
 17590  3.51    July 1748 19712  3.10 
 August  1983  21786
 3.70*    August 1700 21370 3.05 
 September  2066  26909  4.54*
   September 1645 19371  3.24 
 October  1800
 23202
 4.31*
   October 1717 21114  3.20 
 November  1852
 24468
 4.19*
   November 1570 17362 3.09
 December  1690
 20576
 3.78
   December 1924 22842 3.44
*8,000 spl drinking water lead project



Average Days   
to Complete 
Average Days   
to Complete